Multi-source offshore renewable energy parks, where wave & offshore solar energy are integrated in an offshore wind park, are greatly beneficial to the energy transition. Understanding that the large-scale deployment of such parks is largely dependent on the right policy frameworks and on efficient engagement with local stakeholders, the Dutch Marine Energy Centre (DMEC), POM […]
Preparatory Phase (2021-2022)
A front-end engineering design study (FEED) is performed. It assesses (1) the environmental impact, (2) detailed cost analysis and (3) technical design to install a 3 MW offshore solar PV system. During this preparatory study, all permits to build the offshore grid connection and deploy the floaters will be obtained. The preparatory study is planned to be concluded in October 2022.